vineri, 20 mai 2011

First floor walls!

In these days we are working at first floor walls. We aim to finish first floor red stage until next friday. We had a couple of rainy days but we are on schedulle!


vineri, 13 mai 2011

Ground Floor Red Stage Reached!

Today we put the concrete over the Ground Floor and we consider this an achievment for one month of work included Easter Holiday and Sundays. Three time faster then first time! From monday we will start to build First Floor! We made also first steps in order to build the fence by buying fence posts and signing the contract for buying the wood from 200km of Bucharest, in a forest region. Enjoy the pictures!








sâmbătă, 7 mai 2011

Ground floor walls finished!









We continue the work in order to prepare wood panels and iron for the concrete layer between ground floor and first floor. We aim to finish ground floor until next tuesday. In paralel we start to work for the fence. This week we forced to stop the work one day due to weather conditions.